Project Updates
The City of Brooklyn Center is preparing for the full-depth pavement replacement of Humboldt Avenue between 69th and 65th and the mill and overlay of 65th Avenue between Humboldt and Camden.
Last Updated: 9/18/2025
To address neighborhood safety concerns, reduce traffic delay, and create safer routes to school, the project now includes:
- Three single-lane roundabouts are designed to calm traffic, reduce crashes, and smooth traffic flow. They are located at:
- 69th Ave N and Humboldt Ave N
- Humboldt Ave N and 65th
- 65th Ave N and Dupont Ave
- Pedestrian and bicycle upgrades—high-visibility crosswalks, ADA-compliant curb ramps, curb extensions, and improved sidewalk connections—to make it easier for students to walk and bike to Brooklyn Center High School and Middle School.
- Street rehabilitation and utility replacements within the project limits, extending pavement life and improving underground infrastructure.
Project Schedule
- February 2027: Anticipated Bid Opening
- April 2027: Start Construction
- November 2027: End Construction
Contact Information
Please contact the Public Works Planner for all project coordination issues and information:
Kory Andersen Wagner
Public Works Planner
763.569.3329
Utility Outages
Please contact the following for utility outages:
- CenterPoint Energy gas leak: (612) 372-5050
- Xcel Energy electric outage: 1 (800) 895-4999
- CenturyLink: 1 (800) 954-1211
- Comcast: 1 (800) 934-6489
- City of Brooklyn Center 7:00 a.m. - 3:00 p.m. (763) 585-7100
- After hours, call 911 (the dispatcher will contact the appropriate on-call service staff